19.01.2012

Scheduled progress despite freezing cold

Sales Centre of ESI China 1 project is taking shape

The main framework of the Sales Centre of the ESI China 1 project could be completed earlier than expected. Actually, the sales office has already passed the quality test of local government building inspection. The building was erected during the entire winter season, i.e. under comparatively unfavourable weather conditions.

Thus, construction works continued even in bitterly cold conditions until 27 December. Despite the difficult situation in the winter construction site, quality inspectors confirmed the construction high standard. This proves once again that the ESI team has the on-site situation under control and it consistently complies with the targets also in the investors' interest.

The two-story sales centre is designed for a total area of ​​approximately 2,100 square feet and nearly 12.5 meters high. The unusually large height allows the refined European design elements such as the ancient Greek translucent, massive columns, the spacious window sections, or even the long Roman balustrade to show to significant advantage.

The detail plans to the decorated interior works shall be prepared within the next weeks so that works may begin again, as soon as temperatures allow it. The construction and installation activities for this showpiece will be completed in their entirety later this summer.